⚠️ Emergency Alert 06-04-2025: Construction Zone Safety While we know that it is exciting to have a construction project going on in New Richland, it is very important for everyone to maintain a safe distance from the construction site. For that reason, “Stay safe by staying out”. We are seeing an increase in people near the construction zones appearing to try and see what is going on. This can put these individuals at risk of serious injuries. These areas have large trucks and heavy equipment working in close quarters, uneven ground and other hazards. Staying out of the works zones helps keep everyone safe and lets the contractors do their work efficiently. Please remind everyone to stay out of the work zones. The City of New Richland will try to provide updates as often as possible regarding the 2025 Street and Utility Project.

Project Updates

Homes and businesses in the project area will be notified via door hangers and newsletters.  The city will also utilize Facebook and our city notification system to make notifications regarding the project and any updates within the project area.  You can sign up for notifications here.

Construction Progress Update – Week of June 16th:

  • The contractor finished main line sanitary sewer and began watermain along Ash Ave S.
  • Private utilities have continued the relocation of their facilities near the project areas.
  • The contractor began setting out a temporary water system along Broadway Ave S on June 20th. Residents will be notified prior to any switch over or interruptions.

 

Planned Construction Schedule Update – Week of June 23rd:

  • The contractor plans to continue watermain and work on sewer and water services along Ash Ave S and 4th St SW.
  • There is a water shut down for residents along Ash Ave S that are located south of 4th St SW tentatively planned for Wednesday, June 25th. The residents impacted will be notified when the plan is confirmed.
  • The intersection of Ash Ave S and 4th St SW will be closed when underground utility work is happening in the intersection. Those residents being impacted will continue to be notified the day prior to any closure.
  • In conjunction with the city’s project, private utility companies will be continuing to relocate their facilities near the project area. If interruptions are expected, the utility companies will communicate these with customers.

___________________________________________________________________________________________________________________________________________________

Construction Progress Update – Week of June 9th:

  • The contractor began underground utility work along Ash Ave S working north to south.
  • A water shutdown to isolate the Stage 1 watermain was completed and residents in the affected areas have been switched over to temporary water.

 

Planned Construction Schedule Update – Week of June 16th:

  • The contractor plans to continue underground utility construction along Ash Ave S and also begin utility construction along 4th St SW.
  • An intersection closure of 4th St SW and Ash Ave S is tentatively planned for Tuesday, June 17th (weather dependent). Door hangers will be delivered on Monday to confirm the closure.
  • In conjunction with the city’s project, private utility companies will be continuing to relocate their facilities near the project area. If interruptions are expected, the utility companies will communicate these with customers.

_____________________________________________________________________________________________________________________________

Planned Construction Schedule Update-06/09/2025

  • If the temporary water test passes, the contractor will begin contacting residents to connect services to the temporary water system.
  • The contractor plans to begin underground utility work on Tuesday, June 10th. This work will involve a temporary water shutdown for some residents & a temporary closure of the intersection of Ash Ave S & 4th St SW. Notifications will be delivered to the specific properties affected on Monday, June 9th.
  • In conjunction with the city's project, private utility companies will also be relocating their facilities near the project area. If interruptions are expected, the utility companies will communicate these with customers. 

_______________________________________________________________________________________________________________________________

Construction Progress Update-06/02/2025

  • Tree removals have been completed for all stages of the project. Some additional cleanup will occur during the week of June 9th.
  • The contractor has completed most of the surface removals of stage 1 construction (Ash Ave S & 4th St SW
  • Temporary water has been set out and sampled for testing. 

___________________________________________________________________________________________________________________________________

Construction Startup Notice - 5/29/25

Newsletter #1 - 5/27/2025